Pembangunan RPTRA Johar Baru Capai 42 Persen
.
photo Wuri Setyaningsih - Beritajakarta.id

Johar Baru Construction Has Touched 42 Percent

The stage of drying or construction strengthening is very important. Hence the process can take place 10 days

The construction of Johar Baru RPTRA, Central Jakarta has reached 42.91 percent. It is targeted to be completed in the upcoming October.

"The stage of drying or construction strengthening is very important. Hence the process can take place 10 days," expressed Muhammad Fahmi, Assistant for Central Jakarta People's Welfare, Tuesday (9/19).

RPTRA Construction Progress in Cengkareng Has Reached 50 Percent

According to him, if it is not completed optimally, it will not last long and quickly collapse. "If it's not maximal, the building can collapse," he expressed.

Meanwhile, Johar Baru Urban Village Head added RPTRA with 500 square meters width would have a jogging track. Thus local people can use to exercise.

"If there is no obstacle, it will be inaugurated on October 10," he stated.

Linked News
Popular News indeks
  1. Free Additional Nutritious Food Distributed to 31 Toddlers in Kalibata

    access_time13-09-2024 remove_red_eye1146 personTiyo Surya Sakti
  2. Jakarta Women's Football Team Ready to Face West Java at PON XXI Final

    access_time13-09-2024 remove_red_eye845 personFolmer
  3. Water Channel Dredging on Bendungan Melayu Reaches 50 Percent

    access_time18-09-2024 remove_red_eye826 personAnita Karyati
  4. Jakarta Leads Medal Standing at PON XXI

    access_time17-09-2024 remove_red_eye775 personFolmer
  5. PON XXI Temporary Standings: Jakarta Continues to Shadow East Java

    access_time13-09-2024 remove_red_eye754 personAldi Geri Lumban Tobing